Projects across UK & Scotland
A selection of flagship UK infrastructure projects showcasing my experience in site engineering, setting out, QA and site management across highways and major civils delivery.
AWPR Aberdeen Western Peripheral Route
- Setting out, levels, surveys and as-built verification
- QA / ITP support: inspections, records and compliance checks
- Earthworks, drainage, kerbs and pavements delivery support
- Coordination of traffic management and safe work interfaces
- Day-to-day supervision of gangs and subcontractors
- Materials planning, ordering and progress reporting support
Stonehaven Flood Protection Scheme
- Setting out and level control for flood defence works
- CFA/drilled concrete piles: set-out, checks and as-built records
- RC walls: formwork, rebar and pour QA support
- Coordination of earthworks, drainage and temporary works
- Progress tracking and materials planning/support
A14 Cambridge to Huntingdon Scheme
- Setting out, levels and as-built verification (highways works)
- Slipform operations support: line/level control
- Pavements and kerbs: setting out and QA / ITP checks
- Drainage and earthworks interfaces: coordination and measurements
- Daily coordination with gangs/subcontractors, progress reporting
The Viking Energy Wind Farm Shetland
- Setting out for wind turbine bases, crane pads
- Access track construction: alignments, levels and QA checks
- Drainage works: ditches, culverts and outfalls
- Earthworks control: cut / fill checks, formation verification and as-built records
- Concrete works support: rebar/formwork checks and pour QA (bases / ancillaries)
High-Speed Rail (UK) – Major Infrastructure Project
- Section Engineer support on major rail infrastructure works
- Temporary Works coordination: design checks, permits, inspections and compliance
- Stabilised embankment works: formation control, materials verification and compaction QA
- Earthworks interfaces: coordination of crews/subcontractors and daily site reporting
- Progress tracking and look-ahead planning for temporary works and earthworks activities
A30 Chiverton to Carland Cross
- Setting out and engineering support for A30 Chiverton to Carland Cross highway works (alignment, levels and control)
- Earthworks supervision: cut/fill checks, formation verification and compaction / plate testing QA support
- Drainage works: setting out trenches, manholes, carrier drains, headwalls/outfalls and as-built records
- Road construction: sub-base/base course levels, kerb lines, tie-ins and surfacing prep checks
- QA documentation: ITP inspections, NCR/permit support where required, redline updates and survey/as-built deliverables
These projects reflect hands-on delivery experience across highways, rail, wind farms and flood protection — from setting out and QA to earthworks, drainage and concrete works. If you need reliable site engineering support or drone surveying deliverables, get in touch and I’ll respond quickly.